Continuous One Piece Flow

Per Wahrén  4 January 2010 12:24:29

Image:Continuous One Piece Flow
Productivity
The EWAB system above increased productivity by more than 25% when only 20% was installed and used in full production. Work-in-process decreased to 10% of what it was before the investment.

The production capacity with this investment doubled and installation and re-allocation of machines were carried out during full production. No loss of production was measurable during the installation period.

The whole production facility was re-arranged, about half of the machines were added and the EWAB system was installed during a time period of about four months.
Flexibility
The system above handles about 100 different part numbers divided into four families. These four families are produced at random and simultaneously in the system.

Some resources are dedicated to a certain family, some resources are changed over depending on need and some resources can take any part either in batches or totally at random.

The modularity of the system allowed the customer to change their mind even after the equipment was loaded on to delivery trucks. The entire system was installed mirror image to the original layout.
Ewab Integration Technology
Ewab Engineering have been integrating industrial automation since the dawn of automation 40 years ago.

Well proven interfacing with hundreds of OEM's allows the focus to be on the parts to be handled, the installation site and the operators.

Ewab Integration Technology
builds on three corner stones:

>> Teamwork Across Borders,
>> Customer Controlled Turnkey
>> Life Performance Guarantee.

Ewab Conveying Technology
We can handle parts weighing from grams to several tons in manufactturing as well as assembly